摘要
随着造船理念的更新,船舶工业生产方式越来越趋向于总段大型化,以缩短造船周期,降低造船成本。文章通过对国内船厂利用大型龙门吊与现有龙门吊进行生产的对比,分析总段大型化后对船坞周期产生的影响。
With the development of the concept of shipbuilding, in order to reduce the shipbuilding costs, shorten shipbuilding cycle, the block is becoming more and more large-scale. This paper compares with the production cycle between using the large gantry and existing gantry, analysis the effects of the dock cycle when the blocks have been bigger.
出处
《船舶工程》
北大核心
2015年第10期94-97,共4页
Ship Engineering
关键词
大型总段
龙门吊负荷率
搭载周期
large block
load rate of gantry crane
erection period