摘要
以大连中远船务9000HP PSV项目为例,结合《海洋石油支持船监造技术指导书》、《全回转推进器安装工艺》等要求,分析研究PSV全回转推进器的安装难点,并根据船厂生产设备情况及建造工艺水平,提出了推进器的安装方法并优化了设计方案,为其它同类海工产品的推进器安装提供宝贵的安装指导经验。
Taking the 9000 HP PSV built by COSCO Dalian shipyard as an example, according to the instruction of platform supply vessel supervision and installation procedure of azimuth thruster, the design essentials of azimuth thruster installation are researched. According to the shipyard production equipment and construction technology, it is proposed the thruster installation method and optimized design scheme, which providing valuable experience for other similar marine engineering project design and construction.