介绍了双沟水电站引水系统建筑物的总体布置,引水系统布置充分考虑了地形、地质和交通条件,布局合理、安全经济、运行管理方便,并采取了多项设计优化措施,减少了工程量,加快了施工进度,节约了工程投资。取得经济效益和社会效益。
The general layout of the headrace system of Shuanggou Hydropower Project is described. The layout of the headrace system, with full consideration of topography, geology and access conditions, is rationally arranged. It is safety, economic and convenient for operation management. Furthermore, a couple of design optimizing measures are taken so that work quantity is reduced, construction is expedited and investment is decreased. Both economic and social benefits are achieved.
出处
《西北水电》
2015年第5期33-35,共3页
Northwest Hydropower
关键词
双沟水电站
进水口
引水隧洞
调压井
压力管道
Shuanggou Hydropower Project
power intake
headrace tunnel
surge shaft
penstock