期刊文献+

铁路隧道软弱围岩浅埋段的施工工艺研究 被引量:1

Study on construction technology of railway tunnel at soft surrounding rock shallow-buried section
下载PDF
导出
摘要 结合铁路隧道工程的模拟建设情况,对CRD施工方法和大拱脚台阶法两种施工工艺进行了对比分析,指出大拱脚台阶法的施工效果优于CRD施工方法,并就铁路隧道软弱围岩浅埋段的施工技术要点进行了研究,以期为今后的铁路隧道建设提供参考借鉴。 Combining with railway tunnel engineering simulating construction conditions,the paper compares and analyzes two construction technologies of CRD construction method and large-arch-foot benching method,and points out that: the construction effect of large-arch-foot benching method is superior to that of CRD construction method,and studies construction technology points of railway tunnel at soft surrounding rock shallow-buried section,with a view to provide some guidance for railway tunnel construction in future.
作者 刘岩松
出处 《山西建筑》 2015年第32期151-152,共2页 Shanxi Architecture
关键词 铁路隧道 软弱围岩 浅埋段 施工工艺 railway tunnel soft surrounding rock shallow-buried section construction technology
  • 相关文献

参考文献3

共引文献4

同被引文献2

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部