基于活动延期风险加权时差的资源受限项目调度鲁棒性度量 被引量:6

Robustness Measure for the Resource-constrained Project Scheduling Problem based on Activity Delay Risk Weighted Slack
下载PDF
导出
摘要 在项目调度鲁棒性研究中,当活动出现延期风险时,由于各活动性质不同,其延期风险权重也不同,权重越大的活动越有可能影响项目的完工时间。针对资源受限项目调度问题,提出一个基于活动延期风险加权时差的鲁棒性度量新指标。在出现不确定因素干扰时,该指标不仅考虑了活动延期风险权重的影响,同时为实现时差在多个任务之间的共享,还考虑了紧前任务数量的影响。建立一个以加权时差最大化为目标的资源受限项目调度鲁棒优化模型,并针对模型特点,设计了基于禁忌搜索的模拟退火算法。最后,通过算例验证了该度量方式和算法的合理性和有效性,对比分析结果表明所提出的指标优于现有的度量指标,较好地满足了项目调度质量鲁棒性的要求。 During the research on the robustness of project scheduling, each activity of the project has different weight of delay risk because of its different nature when it appears delay risk. The higher the weight is, the more likely the activity will affect the makespan of the project. In view of the resource-constrained project scheduling problem, a new robustness measure index based on activity delay risk weighted slack is put forward. When un- certain factors appear, this index not only considers influences of the weight of delay risk, but also takes the number of preceding activities into account to realize the share of slack among multiple activities. A robust opti-mization model for the resource - constrained project scheduling problem aimed at weighted slack maximization is developed. According to the feature of the model, a simulated annealing algorithm based on the tabu search is presented. Finally, the results of the numerical example validate the reasonableness and the effectiveness of the measurement and the algorithm. Also, the superiority of the newly proposed index over the old ones is proven by comparison results and it can meet the demands of quality robustness of the project scheduling better.
出处 《运筹与管理》 CSSCI CSCD 北大核心 2015年第5期167-174,共8页 Operations Research and Management Science
基金 中央高校基本科研业务费专项资金(15CX05007B 15CX04102B 15CX08012A 14CX06037B) 国家自然科学基金资助项目(71501188) 山东省自然科学基金资助项目(ZR2015GM009)
关键词 项目调度 鲁棒性 延期风险权重 时差 模拟退火 project scheduling robustness weight of delay risk slack simulated annealing
  • 相关文献

参考文献13

  • 1Al-Fawzan M A,Haouari M.A bi-objective model for robust resource-constrained project scheduling[J].International Journal of Production Economics,2005,96(2);175-187.
  • 2Van De Vonder S,Demeulemeester E,Herroelen W,Leus R.The use of buffers in project management:the trade-off between stability and makespan[J].International Journal of Production Economics,2005,97(2):227-240.
  • 3Van De Vonder S,Demeulemeester E,Herroelen W,Leus R.The trade-off between stability and makespan in resource- constrained project scheduling[J].International Journal of Production Research,2006,44(2):215-236.
  • 4Van de Vonder S,Ballestin B,Demeulemeester E,Herroelen W.Heuristic procedures for reactive project scheduling[J].Computers & Industrial Engineering,2007,52(1):11-28.
  • 5王勇胜,梁昌勇.资源约束项目调度鲁棒性研究的现状与展望[J].中国科技论坛,2009(8):95-99. 被引量:5
  • 6Abbasi B,Shadrokh S,Arkat J.Bi-objective resource-constrained project scheduling with robustness and makespan criteria[J].Applied Mathematics and Computation,2006,180(1):146-152.
  • 7Kobylanski P,Kuchta D.A note on the paper by M.A.Al-Fawzan and M.Haouari about a bi-objective problem for robust resource-constrained project scheduling[J].International Journal of Production Economics,2007,107(2):496-501.
  • 8Chtourou H,Haouarib M.A two-stage-priority-rule-based algorithm for robust resource-constrained project scheduling[J].Computers & Industrial Engineering,2008,55(1):183-194.
  • 9Khemakhem M A,Chtourou H.Efficient robustness measures for the resource-constrained project scheduling problem[J].Int.J.Industrial and Systems Engineering,2013,14(2):245-267.
  • 10Lambrechts O,Demeulemeester E,Herroelen W.A tabu search procedure for developing robust predictive project schedules[J].International Journal of Production Economics,2008,111(2);493-508.

二级参考文献57

  • 1曹杰,杨晓光,汪寿阳.突发公共事件应急管理研究中的重要科学问题[J].公共管理学报,2007,4(2):84-93. 被引量:104
  • 2J Gordon and A Tulip.Rsource scheduling [J].Journal of Project Management, 1997(15):359-370.
  • 3E. Demeulemeester, W. Herroelen. Project Scheduling: A Research Handbook[M], Boston, Kluwer Academic Publishers, 2002.
  • 4P. Brucker, A. Drexl, R. Mohring, K. Neumann, E. Pesch. Resource-constrained project scheduling: notation, classification, models and methods[J], European Journal of Operational Research. 1999, (112) :3 -41.
  • 5Daniel W M Chan. A comparative study of causes of time overruns in Hong Kong construction project [J].Journal of Project Man- agement, 1997,(15):55-63.
  • 6Sadi A.Assaf.Causes of delay in large construction project [J]. Journal of Project management, 2006,(24):349-357.
  • 7Albert R ,Barab'asi A - L. Statistical mechanics of complex networks[J] . Rev Mod Phys , 2002 , 74 : 47 - 97.
  • 8Albert R, Jeong H , Barab'asi A - L. Attack and error tolerance of complex networks[J] . Nature , 2000,406 : 378 - 382.
  • 9Newmann M E J . The structure and function of complex networks[J] . SIAM Rev, 2003, (45): 167 - 256.
  • 10Christian Artigues , Jean-Charles Billaut, Cad Esswein. Maximization of solution flexibility for robust shop scheduling [J]. European Journal of Operational Research, 2005, (165): 314 -328.

共引文献23

同被引文献31

引证文献6

二级引证文献22

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部