摘要
大板梁吊装是大型电厂锅炉施工的重点。由于大板梁吊装具有特殊性,因此,需要制订完善的方案,以保证施工安全,从而更好地控制施工作业,降低施工成本。
The girder hoisting construction of large power plant boilers. The plate girder hoisting has particularity. Therefore, it is necessary to formulate a perfect scheme to ensure the safety of construction, thus better control operation, reduce the construction cost.
出处
《科技与创新》
2015年第22期152-153,共2页
Science and Technology & Innovation
关键词
电厂
大板梁吊装技术
锅炉
履带吊
power plant
girder hoisting technology
boiler
crawler crane