软土地层中顶管施工顶进力计算分析

Jacking Force during Pipe Jacking in Soft Soil
下载PDF
导出
摘要 在顶管施工过程中,管材受到各种外力的作用,千斤顶的顶推力尤为重要。顶进力一般由顶进过程中受到的阻力来进行估算,顶进阻力主要包括切削刀盘受到的迎面阻力和管壁与土体之间的摩擦阻力。根据实际施工记录,采用数值拟合的方法,提出了适用于在软土地层中采用泥水平衡顶管技术施工,顶进钢管道时的管壁与土体之间单位面积平均摩阻力的计算公式,进而推导出在此情况下的顶进力计算公式,并与目前较为广泛应用的顶进力计算公式的计算结果做了对比,评估合理的参数设置,探讨更加准确的顶进力计算公式。为以后的施工提出一定的指导建议。 During a pipe jacking engineering, there are so many kinds of forces loaded on the pipe, which are particularly important. Jacking force is usually estimated by the resistance including the face resistance of the cutting head and the frictional resistance between the pipe and the soil. According to the Hong Kong-Zhuhai-Macao Bridge, Zhuhai Gongbei tunnel project, a more suitable formula which can calculate the frictional resistance between the pipe and the soil when using slurry machine to excavate in the soft soil has been put forward by using numerical fitting method, and then deduced the formula which can estimate the jacking force. In addition, this paper compared the result of the formulas which are more widely used and the new formula to find the reasonable parameters and to explore more accurate formula of jacking force calculation. So, it can make some suggestions for future constructions.
作者 郑聪
出处 《非开挖技术》 2015年第3期40-43,共4页 China Trenchless Technology
关键词 顶管 顶进力计算 摩阻力 数值拟合 Pipe Jacking Jacking Force Frictional Resistance, Numerical Fitting
  • 相关文献

参考文献5

  • 1KimberlieStaheli interface friction Jacking force predic-tion:An approach based on pipe surface rough-ness [D].Atlanta:Georgia Institute of Technology,2006.
  • 2Pellet, A.-L., Kastner, R., 2002. Experi-mental and analytical study of friction forces during microtunneling operations. Tunnelling and Underground Space Technology 21,668-683.
  • 3GB50268-2008给水排水管道工程施工及验收规范[S].
  • 4中国非开挖技术协会顶管施工技术及验收规范[s].
  • 5日本下水道管渠推进技术协会(JMTA).推进工法应用编[S].

共引文献124

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部