摘要
针对翠宏山铁多金属矿井筒多、开采水平多、土建施工时间短的特点,结合施工现状,从分析矿山主要矛盾入手,对各水平施工顺序、溜破系统、主副井井塔施工时间、永久装备时间等进行优化。
Optimization was conducted of construction sequence at levels and ore pass fragmenting system as well as construction time and permanent equipment time for the main and auxiliary shaft headframes , proceeding with analyzing the principal contradictions in the mine in light of features of multiple pit shafts and mining levels, short construction time and current situations of construction in Cuihongshantie Polymetal Mine.
出处
《化工矿物与加工》
CAS
北大核心
2015年第11期57-59,共3页
Industrial Minerals & Processing
关键词
溜破系统
施工顺序
永久装备
ore pass fragmenting system
construction sequencer;permanent equipment