黄河丁坝土工织物软体排的施工技术分析

Analysis on Construction Technique of Yellow River T-dam Geotextile Soft Mattress
下载PDF
导出
摘要 分析了黄河丁坝防护工程的土工织物软体排的施工技术,排体的布置范围、分块搭接与坝前冲刷坑的形状、深度、大小有一定的关系。软体排的平面尺寸取决于坝前冲刷坑的最终稳定深度和坡度。进行了冲刷坑深度、软体排的长和宽的计算,探讨了丁坝软体排的布置方式及排体的分块和搭接工艺。 It analyzes and finds out that the geotextile soft mattress construction techniques, layout range and block-overlap of the Yellow River T-dam protective engineering have certain relations with the shape,depth and size of scour pit in front of the T-dam. The plane dimension of soft mattress depends on the ultimately stable depth and slope of scour pit in front of the T-dam. The depth of the scour pit and the length and width of soft mattress have been calculated, as well as the soft mattress layout form and blockoverlap techniques of the mattress body have been discussed.
出处 《黄河水利职业技术学院学报》 2015年第3期1-4,共4页 Journal of Yellow River Conservancy Technical Institute
关键词 黄河丁坝 土工织物软体排 施工布置 分块搭接工艺 Yellow River T-dam geotextile soft mattress construction layout block-overlap technique
  • 相关文献

参考文献3

  • 1《堤防工程土工合成材料应用技术》编写组.堤防工程土工合成材料应用技术[M].北京:中国水利水电出版社,1999:54.
  • 2GB50286-2013,堤防工程设计规范[S].2012.
  • 3SL/T225-98.水利水电工程土工合成材料应用技术规范[S].[S].,1998..

共引文献123

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部