期刊文献+

基于遗传算法的柔性机器人制造单元调度问题研究 被引量:12

Research of Flexible Robotic Manufacturing Cell Scheduling Problem Based on Hybrid Genetic Algorithm
下载PDF
导出
摘要 考虑机器人在装载站、机床、卸载站三者间搬运时间和空载时间的情况下求解柔性机器人制造单元Job-shop类型调度问题,目标是求所有工件加工完成并搬至卸载站的最短时间。首先,在分析机器人制造单元调度问题特点的基础上建立其数学模型,提出了一种新的对机器人搬运工序排序组成搬运序列矩阵的调度方法,机器人按搬运序列搬运,机床则按先到先服务规则(FCFS)加工;然后针对这种调度方法提出了一种改进遗传算法,为遗传算法设计了一种基于搬运工序编码方法与启发式分配策略,设计了一种启发式搬运矩阵调整方法,最后,把启发式调整算法与遗传算法结合组成混合算法对调度问题进行求解,通过标准算例计算,验证了算法的有效性。 Considering the transport time of robot among loading station machine and unloading station to solve flexible robotic manufacturing cell scheduling problem. The goal is to find the shortest time for all workpiece is completed and moved to unload station. Firstly,mathematical model is established based on analysis of the characteristics of flexible robot manufacturing cell scheduling problems. A newscheduling method based on sequence matrix of robot transport operation is proposed,machine processing is based on first come first serve rule( FCFS); Then,an improved genetic algorithm is proposed for this scheduling method,handling procedure code method and heuristic assignment strategy for genetic algorithm is designed,heuristic handling sequence adjustment algorithm is proposed; Finally,heuristic algorithm is combined with genetic algorithm to build hybrid algorithm to solve this scheduling problem,through the standard example calculation,verified the effectiveness of the algorithm.
出处 《组合机床与自动化加工技术》 北大核心 2015年第11期141-144,148,共5页 Modular Machine Tool & Automatic Manufacturing Technique
基金 国家自然科学基金资助项目(51105082) 国家科技支撑计划资助项目(2012BAF12B10) 广东省战略性新兴产业核心技术攻关资助项目(2011A091101003)
关键词 机器人制造单元 JOB-SHOP 混合遗传算法 flexible robot manufacturing cell Job-Shop HGA
  • 相关文献

参考文献11

  • 1王凌,郑大钟.基于遗传算法的Job Shop调度研究进展[J].控制与决策,2001,16(B11):641-646. 被引量:34
  • 2熊禾根,李建军,孔建益,杨金堂,蒋国璋.考虑工序相关性的动态Job shop调度问题启发式算法[J].机械工程学报,2006,42(8):50-55. 被引量:33
  • 3潘全科,王文宏,潘群,朱剑英.解决JOB SHOP问题的粒子群优化算法[J].机械科学与技术,2006,25(6):675-679. 被引量:10
  • 4何之洲,杨煜俊,陈新度.带搬运机器人的job-shop问题的并行禁忌搜索算法[J].工业工程,2013,16(4):122-125. 被引量:6
  • 5A Caumond,P Lacomme. An MILP for scheduling problems in an FMS with one vehicle [ J ]. Eurpean Joural of Opera- tional Resrarch,2009, 3(51) :706 - 722.
  • 6Philippe L, Mohand L A Disjunctive Graph for the job-shop with several robots [ C ]. MISTA Conference.
  • 7Hurink J, Knust S. Tabu search algorithms for jab-shop problems with a single transport robot [ J ]. European Jour- nal of Operational Research, 2005, 162 ( 1 ) : 99 - 111.
  • 8A Gnanavel Babu, J Jerald, A Noorul Haq. Scheduling of machines and automated guided vehicles in FMS using dif- ferential evolution [ J ]. International Journal of Production Research, 2010,48(16):4683-4699.
  • 9I, DEROUSSI, M GOURGANDz. A simple meta- heuristic approach to the simultaneous scheduling of machines and automated guided vehicles [ J]. International Journal of Production Research,2008, 46(8) :2144- 2163.
  • 10U Bilge, G Ulusoy. A time window approach to sim- ultaneous scheduling of machines and material han-dling system in an FMS [ J ]. Operations Research, 1995,43(6) :1058 - 1070.

二级参考文献56

  • 1王凌.混合优化策略和神经网络中若干问题的研究[M].北京:清华大学,1999..
  • 2王凌 王雄.间歇化工过程最优化的研究进展[J].清华大学学报,2000,40(2):265-269.
  • 3车阿大,晏鹏宇,杨乃定.复杂无等待自动化制造系统的调度算法研究[J].计算机集成制造系统,2007,13(8):1616-1623. 被引量:10
  • 4Eberhart R C,Kennedy J.A new optimizer using particle swarm theory[A].Proc Sixth IEEE International Symposium on Micro Machine and Human Science[C],Piscataway,Nagoya Japan,1995,39~43
  • 5Van den Bergh F.An Analysis of Particle Swarm Optimizers[D].South Africa:Department of Computer Science,University of Pretoria,2002
  • 6Shi Y,Eberhart R C.Empirical study of particle swarm optimization[A].Proceeding of the 1999 Congress on Evolutionary Computation[C],Piscataway,Nagoya Japan,1999,1945 ~ 1949
  • 7Kennedy J,Eberhart R C.A discrete binary version of the particle swarm algorithm[A],Proceedings of the World Multiconference on Systemics,Cybernetics and Informatics[C],Piscataway,Nagoya Japan,1997,4101 ~4109
  • 8Clerc M.Discrete Particle Swarm Optimization Illustrated by the Traveling Salesman Problem[OZ].http://www.mauriceclerc.net,2000
  • 9Tasgetiren M F,Sevkli M,Liang Y C,Gencyilmaz G.Particle swarm optimization algorithm for single machine total weighted tardiness problem[A].Proceedings of the 2004 Congress on Evolutionary Computation[C],June,Portland,Oregon,2004,20-23:1412 ~ 1419
  • 10Sakawa M,Mort T.An efficient genetic algorithm for job-shop scheduling with fuzzy processing and fuzzy duedate[J].Computers & Industrial Engineering,1999,36:325 ~ 341

共引文献77

同被引文献93

引证文献12

二级引证文献69

相关作者