水-光电联合运行短期调度可行性分析 被引量:13

THE FEASIBILITY ANALYSIS OF SHORT-TERM SCHEDULING FOR JOINT OPERATION OF HYDROPOWER AND PHOTOELECTRIC
下载PDF
导出
摘要 针对黄河龙羊峡光伏电站与水电站联合运行短期调度的可行性问题,建立调峰能力最大数学模型,提出基于模拟优化思想的模型求解方法。通过反推机组的最大技术出力论证水光互补对系统调峰能力以及水电站群短期水量调度的影响。实例研究表明:水-光电联合运行短期内可进一步提高系统的调峰能力,且对下游梯级水电站群的日水量调度基本无影响。 To validate the feasibility of the short-term scheduling for the joint operation of hydropower plant and photoelectric plant of LYX, a model aimed at maximizing the peaking capacity was set up. Meanwhile, a method basedon simulation and optimization was used to solve the proposed model. By estimating the maximum technical output of the hydro-photovoltaic system, the impact on hydropower peaking capacity and short-term water regulation was analysed, respectively. Case study reveals that the joint operation of hydropower and photoelectronic could further increase the peaking capacity of the system. In addition, this kind of operation mode has few adverse effects on the short-term water regulation of the downstream cascade reservoirs.
出处 《太阳能学报》 EI CAS CSCD 北大核心 2015年第11期2731-2737,共7页 Acta Energiae Solaris Sinica
基金 水利公益性行业科研专项(201501058) 青海省光伏发电并网技术重点实验室项目(2014-Z-Y34A) 国家自然科学基金(51179148 51179149 51309188)
关键词 水-光电联合运行 短期 调峰能力 水量调度 soint operation of hydropower and photoelectric short-term peaking capacity water regulation
  • 相关文献

参考文献3

  • 1Ma Xiaodi. Study on the acceptance capacity of wind power under the grid peaking constraints [D]. Beijing: Beijing Jiaotong University, 2014.
  • 2谢俊,白兴忠,甘德强.水电/火电机组调峰能力的评估与激励[J].浙江大学学报(工学版),2009,43(11):2079-2084. 被引量:37
  • 3Xie Jue, Bai Xingzhong, Gan Deqiang. Evaluation and incentive mechanism of peaking capability of hydroelectric~thermoelectric generators[J]. Journal of Zhejiang University: Engineering Science, 2009, 43 ( 11 ) : 2079--2084.

二级参考文献9

共引文献36

同被引文献163

引证文献13

二级引证文献94

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部