摘要
根据某大型地下金属矿山基建工程,利用加拿大Surpac软件Minesched模块,编制基建工程施工进度计划流程。经过掘进中线数据准备,定义地质模型,确定井巷掘进断面、基建施工方案及参数设置,最终运行进度计划。进度计划可实现快捷、直观、易调整,对其他地下金属矿山进度编制具有指导和借鉴意义。
According to the situations of the construction engineering of a underground metal mine, based oon Surpae software and Minesched module, the construction schedule planning process of the con- struction engineering is designed. The final construction schedule is obtained by the process of perpetra- ting for excavating midline data, defining geological model, determining mine excavating section and con- struction scheme, setting some relative parameters. The implementation of the construction schedule is simple and can be adjusted easily, besides that, intuitive is also the feature of the construction schedule, therefore, it can provide reference for designing the construction scheme of the other relative underground metal mine.