甘肃迭部县花园水电站1号机组首次并网时水导轴瓦拉瓦事故分析及处理方法

Accident analysis and treatment methods of water guide bearing pad pulling during first grid connected in Gansu Diebu County Huayuan Hydropower Station No.1 Unit
下载PDF
导出
摘要 在甘肃迭部花园水电站1号水轮发电机组首次并网机组带负荷试验时,水导瓦温过高保护动作,机组事故停机。本文通过事故的表现和现场试验的方法,分析了事故的原因及采取的应对措施。通过这一具体事例,充分说明水电站基础埋件二期混凝土的浇筑密实的重要性。 Temperature of water guide bearing pad is too high, thereby leading to protection action during the first grid connected unit load test of Gansu Diebu Huayuan Hydropower Station No. 1 Unit. In the paper, accident causes and adopted countermeasures are analyzed through accident performance and field test method. It fully shows the importance of hydropower station foundation embedded part stage II concrete pouring compaction through this concrete example.
出处 《中国水能及电气化》 2015年第11期47-50,共4页 China Water Power & Electrification
关键词 花园电站 水导瓦 定子基础 Hnayuan Hydropower Station water guide bearing pad stator foundation
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部