期刊文献+

小天都水电站气垫式调压室工程地质勘察研究 被引量:1

Research on air cushion surge chamber engineering geological prospecting of Xiaotiandu Hydropower Station
下载PDF
导出
摘要 小天都水电站采用气垫式调压室方案,除了开展常规地质勘察工作外,着重进行了岩体质量及成洞条件研究、山体抗抬稳定性研究、地应力及围岩抗劈裂稳定性研究、岩体渗透性与围岩抗渗稳定性研究,总结出了在高山峡谷地区引水式电站建气垫式调压室的勘察工作方法与经验。 Xiaotiandu Hydropower Station adopts air cushion surge chamber plan. It not only develops conventional geological prospecting work, but also focuses on the research of rock quality and holes formation condition, mountain lifting resistance stability, ground stress and surrounding rock crack resistance stability, rock permeability and surrounding rock stability. Survey work methods and experience of building air cushion surge chamber on water diversion power station in mountain valley areas are summarized.
出处 《中国水能及电气化》 2015年第11期66-70,32,共6页 China Water Power & Electrification
关键词 气垫式调压室 工程地质条件 地应力 高压压水试验 水力劈裂试验 air cushion surge chamber engineering geological conditions ground stress high pressure water pressuretest hydraulic fracture test
  • 相关文献

参考文献5

二级参考文献4

共引文献9

同被引文献11

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部