沉管钢筋笼劲性骨架制作与安装精度控制 被引量:1

Maufacturing and installation accuracy control of rigid skeleton for steel cage of immersed tube
下载PDF
导出
摘要 以港珠澳大桥沉管隧道管节预制工程为依托,为减小管节预制钢筋笼在整个预制过程中的变形,采取在钢筋笼内部加入劲性骨架的措施。从角钢下料、制作场所、骨架分段定位、焊接变形控制、原材料保护、骨架结构设计等6个方面论述了骨架制作精度控制方法以及底板、墙体、顶板骨架的安装精度控制方法。骨架外形尺寸及安装精度均满足工程要求。 Based on the Hongkong-Zhuhai-Macao Bridge immersed tube element prefabrication project, in order to reduce the deformation of steel cage in the whole process of tube element prefabrication, we took the rigid skeleton in the steel cage. From six aspects including the angel steel blanking, production sites, skeleton segment positioning, welding deformation control, raw material protection, and skeleton structure design, we discussed the manufacturing accuracy control method of skeleton, and the installation accuracy control method of the skeletons on floor, wall, and roof. The overall dimension and installation accuracy of skeleton can satisfy the requirements of engineering.
出处 《中国港湾建设》 2015年第11期113-115,共3页 China Harbour Engineering
关键词 沉管 钢筋笼 劲性骨架 精度控制 immersed tube steel cage rigid skeleton accuracy control
  • 相关文献

参考文献4

  • 1港珠澳大桥管理局.港珠澳大桥主体工程隧道工程施工及质量验收标准[s].2013.
  • 2中交公路规划设计院有限公司.港珠澳大桥主体工程岛隧工程施工图设计:管节结构施工图[R].2012.
  • 3中交股份联合体港珠澳大桥岛隧工程第Ⅲ工区一分区项目经理部.港珠澳大桥沉管预制施工组织设计[R].2012.
  • 4冯伟,戴书学,李凯凯.工厂法预制沉管钢筋笼变形控制[J].中国港湾建设,2015,35(7):14-17. 被引量:8

二级参考文献3

共引文献8

同被引文献2

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部