智能变电站二次系统厂内联调的项目管理改进 被引量:1

Project Management Improvement on the Commission of Intelligent Substation's Secondary Systems
下载PDF
导出
摘要 智能变电站新技术密集、系统架构复杂、回路数字化虚拟化,导致联调持续周期长,耗用人力、物力成本巨大,调试过程复杂、质量难以控制。针对上述问题,运用项目管理方法,对智能变电站调试进行管理上的优化改进,改进前后的联调项目统计数据表明,优化后的管理方法有效地控制了智能变电站的调试成本、缩短了调试周期和提高了调试质量。 Due to the application of many new technologies, complicated system structures and virtual electrical secondary circuits, the commission of intelligent substation becomes a long period, much manpower, complicated commissioning process and quality hard to control project. In this paper, the method of project management is used to improve the management of intelligent substation. By analyzing the statistical data between before and after using the method, it is found that the improved management can shorten the period, promote the quality and control the costs effectively.
出处 《江苏电机工程》 2015年第6期74-76,81,共4页 Jiangsu Electrical Engineering
关键词 智能变电站 项目管理 成本控制 人力资源 intelligent substation project management costs control human resource
  • 相关文献

参考文献8

二级参考文献23

共引文献226

同被引文献9

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部