摘要
由于双江口水电站的坝高、水库面积大以及地形复杂等因素,大大制约了过鱼设施的布置。本文结合双江口水电站枢纽工程布置、水库情况和鱼类资源等特点拟定了4种过鱼方案进行比选,选定了适合该工程实际的过鱼措施,是国内同类型项目的第一次尝试,研究所得成果对同类工程有一定的借鉴作用。
Due to the high dam height, large reservoir area and complicated landform, the arrangement of fish passage facility is largely restricted for Shuangjiangkou Hydropower Station. Combined with the characteristics of the hydropower station, such as the project layout, the condition of the reservoir, the fish resources, etc. , 4 fish passage schemes are comparatively selected, and then a fish passage measure suitable for the actual condition of the project is determined, which is the first trial within the similar projects in China and the result from the study can provide certain references for the similar projects as well.
出处
《水利水电技术》
CSCD
北大核心
2015年第11期19-22,共4页
Water Resources and Hydropower Engineering
基金
"十二五"国家科技支撑计划:重点水利水电工程生态保护技术及标准规范研究(2012BAC06B01)
关键词
双江口水电站
过鱼设施
方案比选
Shuangjiangkou Hydropower Station
fish passage facility