摘要
在BIM技术运用的基础上,运用系统工程理念,首次提出BIM+理论进行船闸工程的建设。通过BIM技术与3D打印、三维水流数值模拟、互联网等技术的有机结合,进行船闸工程的规划分析、设计优化、施工组织及运维管理等工作,实现了基于BIM+理论的船闸工程建设新模式。工程实践表明,该模式简单高效,破解了船闸工程复杂结构建设的难题,具有广阔的应用前景,可为类似工程提供理论指导与技术借鉴。
Based on the systematic engineering concept, we put forward for the first time the theory of Building Information Modeling (BIM) plus to guide the ship lock construction. Integrating BIM and 3-D printing, hydraulic simulation and internet, we carry out the planning, design, construction and operation management of the ship lock project and thus realize a new mode for constructing the ship lock based on BIM plus. The engineering practices prove that this new mode is simple with high efficiency, and solves the construction difficulties of complex ship lock structure easily. Therefore this mode has a vast application prospect and may serve as the theoretical guide and technical reference for similar projects.
出处
《水运工程》
北大核心
2015年第12期123-127,共5页
Port & Waterway Engineering
基金
住房城乡建设部2014科学技术项目计划(2014-S1A-003)