提出了一种基于Promis·e设计环境的变电站电工二次专业协同设计方法,对协同平台的建立、制图标准化、设备模型库构建以及协同设计流程等协同设计中的一些关键环节进行了描述,并结合工程实践,给出了协同设计各关键点的应用实例及解决方案。所提出的变电站二次接线协同设计方法,已经在10余座220 k V的变电站项目中得到了应用,它可以大幅度地提高设计效率,保证设计成果的质量,具有继承性、拓展性和参照性。
A professional collaborative design methodology for secondary wiring of substation based on Promise- e design software is proposed. Key points including the establishment of the collaborative platform,the standardization of drawing,the construction of equipment model library,and the procedures of collaborative design are described,and the application and solutions of the above key points are provided in combination with some engineering practices. The collaborative design for secondary wiring has been applied to over ten 220 kV substations and proved capable of significantly improving design efficiency and ensuring the quality of design products. The design method can be inherited and expanded in future use and provide reference for other designs.