本溪衍水斜拉桥主桥塔梁同步平衡法施工技术 被引量:3

The Construction Technology of Synchronous Balance Method of Cable-stayed Bridge Main Beam and Tower of Benxi Yanshui Bridge
下载PDF
导出
摘要 以本溪衍水特大桥主桥钢拱塔与钢箱梁同步施工为例,突破常规斜拉桥塔、梁分离异步式施工方法,应用midas civil有限元软件建模分析及三维模拟技术,施工中合理组织安排塔、梁、索施工顺序,并通过仿真计算与现场实测相结合的方法,实时监测结构应力与线型,采用塔梁同步平衡法施工,提高施工作业效率,降低了施工安全风险,确保了工程质量及工期目标的实现。 Take large bridge tower and steel box girder construction of main span steel arch of Benxi Yanshui Bridge as an example. Break through the conventional separation asynchronous construction method of cable-stayed bridge tower and beam. Need to use finite element software Midas civil modeling analysis and 3D simulation technology. Reasonable to arrange the construction sequence of tower, beam and cable in the process of construction. Through the method of combining the simulation calculation and field measurement. Real-time monitoring the Structural stress and linear. Through the construction method of tower beam synchronous balance.Improve construction efficiency,reduce the risk of construction. To ensure the engineering quality and achieve the goal of the construction period.
作者 阴德辉
出处 《北方交通》 2015年第12期5-8,共4页 Northern Communications
基金 国家自然科学基金项目(51078242) 住房和城乡建设部科学技术项目(2015-R2-027) 高校优秀科技人才支持计划资助项目(LR2013025)
关键词 斜拉桥 塔梁同步 平衡法 施工技术 Cable-stayed bridge Tower beam synchronization Balance method Construction technologye method
  • 相关文献

参考文献2

二级参考文献6

  • 1GB/T3811-2008起重机设计规范[S].
  • 2鞍钢集团钢绳厂.GB8918-2006重要用途钢丝绳[S].北京:中华人民共和国国家质量监督检验检疫总局,2006.
  • 3杨文渊.起重吊装常用数据手册[M].北京:人民交通出版社,2001.
  • 4GB5976-1986,钢丝绳夹[S].
  • 5黎桂英,何悦胜,陶亚秋,等.最新五金手册(修订版)[M].广州:广东科技出版社,2001.
  • 6徐升桥.丫髻沙大桥的非线性分析[J].铁道标准设计,1999,19(8):5-8. 被引量:7

共引文献25

同被引文献18

引证文献3

二级引证文献15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部