基于坝基水泥土防渗的希尼尔水库大坝渗流分析 被引量:1

Seepage analysis of Xi'ni'er reservoir dam with cement soil at dam foundation
下载PDF
导出
摘要 渗流监测是水库大坝安全监测的一项重要内容,其结果对于指导大坝的安全运行管理有着重要意义。以希尼尔水库主坝水泥土防渗墙段为例,对主坝典型断面4+575与5+175进行渗流分析,结果表明:上述两处断面在高库水运行期坝基渗压水位高、渗透压力较大,坝体水位及下游坝后回填清基料出逸点高程较高;排水沟处坝基水平向渗透坡降较大,稍小于坝基土体的允许渗透坡降,并超过反滤垫层料的允许渗透坡降,存在渗流安全隐患。研究结果为指导水库的安全运行提供了重要参考。 Seepage monitoring is an significant content of reservoir dam safety monitoring, and the resultis important for guiding dam operation. Taking Xi'ni'er reservoir main dam cement soil cutoff wall sec-tion as an example, this paper analyzes the seepage of typical section 4+575 and 5+175. The resultsshow that seepage water level and osmotic pressure at dam foundation of these two sections are high, soare dam water level and the elevation of escaping point of backfill base material downstream; horizontalseepage gradient of dam foundation at drainage ditch is relatively large, slightly less than permissiblegradient of dam foundation soil but bigger than filter material's, which means potential safety hazards.The results provide important reference for guiding the safe operation of reservoir.
作者 魏光辉
出处 《大坝与安全》 2015年第6期42-47,共6页 Dam & Safety
关键词 土石坝 渗流分析 水泥土防渗墙 希尼尔水库 earth-rockfill dam seepage analysis cement soil cutoff wall Xi'ni'er reservoir
  • 相关文献

参考文献3

  • 1SL252-2000.水利水电工程等级划分及洪水标准[S].[S].,..
  • 2SL258-2000.水库大坝安全评价导则[S].[S].,..
  • 3中华人民共和国水利部.GB50487-2008水利水电工程地质勘察规范[S].2008.

共引文献257

同被引文献2

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部