期刊文献+

南水北调京石段测压管渗透性检测分析 被引量:1

Design of penetration inspection for piezometric tube on BeijingShijiazhuang section of the Mid-route of South-to-North Water Diversion Project
下载PDF
导出
摘要 为了掌握总干渠渗流情况,为总干渠安全运行提供必要信息,南水北调京石段(河北境内)沿线共布设测压管315根,经统计,其中260根测压管常年无水。选择有代表性的监测断面进行了数据分析,无法准确判断无水测压管是否失效,提出了测压管渗透性检测方案,以查明测压管的有效性。 Up to 315 piezometric tubes were emplaced along with Beijing to Shijiazhuang section of the Mid-route of South-to-North Water Diversion Project to collect the general arterial canal's seepage conditions and provide necessary information for the general arterial canal's safe operation. By statistics, of which 260 of the piezometric tubes were under the water level perennially, which may cause potential safety problems and may do harm to the project. Representative monitor sections were selected for data analysis,but the effectiveness of the piezometric tubes could not be defined. In this article, Monitoring Plan of the piezometric tubes was made to determine their effectiveness.
出处 《水科学与工程技术》 2015年第6期72-74,共3页 Water Sciences and Engineering Technology
关键词 南水北调 测压管 检测 South-to-North Water Diversion Project piezometric tube inspection
  • 相关文献

参考文献5

  • 1河北省水利水电勘测设计研究院.南水北调中线京石段廊急供水工程(石家庄至北拒马河段)初步设计报告[R],2004.
  • 2SL345-2007,水利水电工程注水试验规程[S].
  • 3SL/T5259-2010.土石坝安全监测技术规范[S].
  • 4NSBD-ZGJ-1-1.南水北调中线一期工程总干渠初步设计安全监测技术规定(试行)[S].
  • 5宗志坚.工程安全监测设计[M].郑州:黄河水利出版社,2005.

共引文献24

同被引文献12

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部