电子变压器生产线平衡与瓶颈漂移管理研究 被引量:4

Research on Balance Improvement and Bottleneck Drift Management of the Electronic Transformer Production Line
下载PDF
导出
摘要 针对赣州某电子变压器公司的生产线不平衡及产能低下等问题,对生产现场进行分析及计算工位加工率P识别产线瓶颈,运用MOD法、ECRS原则等工业工程方法与人因工程相关理论,对现行生产线进行平衡改善及优化,提出相应的解决方案,并对产线瓶颈漂移现象提出两点预防措施:合理设置在制品库存量和休息时间。最后运用Enterprise Dynamics仿真软件对生产线进行仿真验证,对比产线改善前后各项平衡指标可知,生产线平衡率、平滑性指数都得到有效改善,产能也有所提升,增加了企业效益。 Based on line imbalance and low capacity of an electronic transformer company in Ganzhou,the bottlenecks are identified by analyzing the production site and calculating working rate P. Then using industrial engineering methods(such as MOD method,ECRS principle,etc.) and human factors engineering theory,the current production line is improved and optimized to put on the propose appropriate solutions. And two preventive measures are also put forward on the bottleneck drift phenomenon: setting up reasonable WIP inventory and rest time. Finally it is simulated a lot through enterprise dynamics simulation software. So that the balance indexes,balance rate,smoothness index and production capacity are improved,which increase the enterprise benefit.
出处 《机械设计与制造》 北大核心 2016年第1期262-264,268,共4页 Machinery Design & Manufacture
关键词 生产线平衡 工业工程方法 人因工程 瓶颈漂移 仿真 Production Line Balance Industrial Engineering Methods Human Factors Engineering Bottleneck Drift Simulation
  • 相关文献

参考文献7

二级参考文献33

  • 1周云霞,刘敏.生产物流中的瓶颈辨识研究[J].物流科技,2005,28(8):11-15. 被引量:12
  • 2李湧范,李从东.工业工程(第四讲) 流程分析及其在机械工业中的应用[J].工程机械,2005,36(12):69-72. 被引量:3
  • 3兰秀菊,陈勇,汤洪涛.SMT生产线平衡的持续改善方析[J].工业工程与管理,2006,11(2):109-111. 被引量:49
  • 4高红花.基于精益生产的标准作业研究[J].机械工业标准化与质量,2007(3):30-32. 被引量:11
  • 5陈荣秋 马士华.生产与运作管理[M].北京:高等教育出版社,2002..
  • 6Christoph Roser, Masaru Nakano, Minoru Tanaka. Shifting Bottleneck Detection: Software Science Laboratory Toyota Central Research and Development Laboratories Nagakute, Aichi ,480 - 1192. JAPAN
  • 7ROSER C,NAKANO M,TANAKA M.Shifting Bottleneck Detection[C]//Winter Simulation Conference,San Diego,CA,USA,2002:1079-1086.
  • 8UMBLE M M,SRIKANTH M L.Synchronous Manufacturing:principle for world class excellence[M].Cincinnati,OH:South-Western pulishing,1990.
  • 9ZHANG RUI,WU CHENG.Bottleneck Machine Identification Based on Optimization for the Job Shop Scheduling Problem[J].ICIC Express Letters,2008(June):175-180.
  • 10SRIDHARAN V,WILLIAM L B,UDAYABHANU V.Freezing the master production schedule under rolling planning horizon[J].Management Science,1992(33):1137-1149.

共引文献49

同被引文献26

引证文献4

二级引证文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部