期刊文献+

西安市第四污水处理厂一期工程升级改造经验总结 被引量:16

Summary of Experience in Upgrading and Reconstruction of First Stage Project of Xi'an Fourth WWTP
原文传递
导出
摘要 西安市第四污水处理厂一期工程于2013年升级改造完成,出水水质标准由《城镇污水处理厂污染物排放标准》(GB 18918—2002)的一级B标准提升为一级A标准。分析了升级改造工程的技术难点,阐明升级改造的技术路线。本次改造最大限度地发挥了现有构筑物的处理能力,尽可能降低对污水厂正常生产运行的影响;成功应用厌氧、缺氧MBBR技术,最大限度地利用生物除磷,减少化学除磷;最终达到降低工程投资、节约运行成本的目的。 The upgrading and reconstruction of the first stage project of Xi' an Fourth WWTP havebeen completed in 2013, and the effluent quality has been improved from the first level B to level A crite- ria specified in the Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant (GB 18918 -2002). The technical difficulties in the upgrading and reconstruction project were analyzed, and the technology roadmap for upgrading and reconstruction was presented. The key contents of upgrading and reconstruction were to maximize the treatment capabilities of existing structures, to minimize the im- pact on the normal operation of the plant, to successfully apply anaerobic and anoxic MBBR technology, to maximize the biological phosphorus removal capacity and to reduce chemical phosphorus removal. The final goals of engineering investment decrease and operating cost saving were achieved.
出处 《中国给水排水》 CAS CSCD 北大核心 2016年第2期74-78,共5页 China Water & Wastewater
关键词 污水处理 升级改造 厌氧 缺氧MBBR 碳源利用 生物除磷 wastewater treatment upgrading and reconstruction anaerobic and anoxic MB-BR carbon utilization biological phosphorus removal
  • 相关文献

参考文献6

  • 1孙梦,张培玉,张晨.城市污水的除磷技术分析[J].水处理技术,2010,36(8):16-20. 被引量:25
  • 2王佳伟,张道友,卢爱国,常江,甘一萍,周军.利用活性初沉池提高生物脱氮除磷能力的研究[J].给水排水,2011,37(S1):78-81. 被引量:2
  • 3曹雪梅,彭永臻,王淑莹.缺氧区、好氧区容积比对A^2/O工艺反硝化除磷的影响[J].中国给水排水,2007,23(3):27-30. 被引量:13
  • 4Kermani M, Bina B, Movahedian H, et al. Application of moving bed biofilm process for biological organics and nu- trients removal from municipal wastewaster[ J ]. Am J En- viron Sci,2008,4(6) :682 - 689.
  • 5Weiss J S,Alvarez M,Chi-Chung Tang C C,et al. Evalu- ation of moving bed biofilm reactor technology for enhan- cing nitrogen removal in a stabilizantion pond treatment plant [ A ]. Proceedings of the Water Environment Federa- tion [ C ]. USA : WEF,2005.
  • 6Kermani M, Bina B, Movahedian H,et al. Biological phosphorus and nitrogen removal from wastewater using moving bed biofilm process[ J]. Iran J Biotechnol,2009, 7(1) :19 -27,61.

二级参考文献42

共引文献37

同被引文献167

引证文献16

二级引证文献87