摘要
通过对矿山立井施工变压器容量一般选择方法的分析,阐明了工程领域采用需要系数法选择设备的局限性,并提出在充分了解施工工艺过程、非常熟悉施工用电设备工作状况的基础上,采用绘制电力负荷曲线的方法能够更合理地选择变压器容量。
The paper illuminated boundedness of using demand coefficient method to choose device in engineering field by analysis of general selection method of transformer capacity of mine vertical shaft,and proposed that using method of drawing electricity load curve in basis of full knowledge of construction technology process and familiar with operating condition of electrical equipment can select capacity of transformer reasonably.
出处
《工矿自动化》
北大核心
2016年第1期67-70,共4页
Journal Of Mine Automation
关键词
矿山立井
变压器容量
需要系数法
电力负荷曲线
mine vertical shaft
transformer capacity
demand coefficient method
electricity load curve