港珠澳大桥预制桥墩裂缝控制技术 被引量:8

Control technology for prefabricated pier crack of Hongkong-Zhuhai-Macao Bridge
下载PDF
导出
摘要 为解决港珠澳大桥CB03标预制桥墩产生裂缝问题,采用有限元仿真模拟分析墩身内部温度和应变状况,在墩身内部埋设温度和应变传感器进行温度和应变原位测试。确定产生裂缝的根本原因是桥墩施工缝上下层混凝土收缩不同步,在此基础上制定了相应的防裂技术措施,较好地解决了裂缝问题。 In order to solve the prefabricated pier crack problems of Hongkong-Zhuhai-Macao Bridge CB03 tenders, we analyzed the internal temperature and strain condition of the bridge pier with the finite element simulation, and buried the internal temperature and strain sensors in the pier to do the in situ test of temperature and strain. We concluded that the root cause of cracks in the production of construction joints piers on the lower shrinkage of concrete are not synchronized, and developed a corresponding crack technical measures, which can well solve the crack problems.
出处 《中国港湾建设》 2015年第12期66-70,共5页 China Harbour Engineering
关键词 港珠澳大桥 预制 桥墩 裂缝 收缩 Hongkong-Zhuhai-Macao Bridge prefabricated pier crack shrinkage
  • 相关文献

参考文献4

  • 1JENSEN Ole Mejlhede. Autogenous defirmation and RH-Chmgc in perspective[J]. Cern ConcRes, 2001(5): 57.
  • 2BAZANT Z P, KIM J K. Consequences of" diffusion theory for shrinkage of cuncrete[J]. Materials and Structures, 1991(2): 1-3.
  • 3JTS202-1-2010,水运工程大体积混凝土温度裂缝控制技术规程[S].
  • 4樊士广,王宇,王新刚.大体积混凝土温度应力仿真分析及防裂措施[J].中国港湾建设,2015,35(7):53-56. 被引量:9

二级参考文献3

共引文献20

同被引文献34

引证文献8

二级引证文献16

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部