针对三百子煤矿1512采区轨道上山布置及巷道断面实际情况,简要介绍适合该矿井的架空乘人装置和异型轨卡轨斜井运人系统,通过对采区上山运人系统技采用架空乘人装置及异型轨卡轨斜井运人系统优缺点对比及技术经济分析,得出采用架空乘人装置可节省设备投资、降低后期运行及维护成本和避免施工工期延误。
According to the rail raise layout and roadway section of 1512 district in Sanbaizi coal mine, this paper introduces the mine personnel transport cable conveyance and profiled trapped rail personnel transport system for inclined shaft, analyzes and compares the advantages, disadvantages and technical economy of both devices, draws a conclusion that, mine personnel transport cable conveyance is preferred in this engineering background with less equipment investment, operation and maintenance costs and shorter construction period.
出处
《煤炭工程》
北大核心
2016年第1期35-36,共2页
Coal Engineering
关键词
架空乘人装置
异型轨卡轨斜井运人系统
巷道断面
采区上山
运输方式
mine personnel transport cable conveyance
profiled trapped rail transportation system of inclined roadway
roadway section
district raise
transportation mode