摘要
论述了为配合汽机房布置的优化,将汽机房内的主厂房6kV配电装置移至A排外。充分利用A列外的有限空间,合理地将其与22kVGIS配电装置、高压厂变等电气设备有机组结合,采用多层布置,并论证这种布置较常规布置具有一定的社会效益。
This paper discuss 6kV substation of turbine house was move to outside column A of the main building. Electrical equipment such as 6kV substation,220 kV substation were multilayer arranged.Outside column A limited space was sufficient utilized.This layout plan is more social benefit than routine layout.
出处
《工程建设与设计》
2016年第2期75-78,81,共5页
Construction & Design for Engineering
关键词
220kVGIS
6kV配电装置
高压厂变
多层布置
220kV gas insulation switch
6kV substation
HV auxiliary transformer
multilayer arranged