台山在建CEPR机组为中广核第三代核电站,机型复杂、冗余度高、设备数量众多。随着工程进入延长期,恶劣环境下更多设备发生腐蚀问题,如何将工程防腐与生产防腐管理进行有效衔接,保障设备完整性和安全、质量可靠性,台山建立了工程生产一体化管理模式,保障了台山核电防腐管理秩序进行。
TNSP CEPR units are the third generation nuclear power plant in the world, and the unit more complex and high redundancy. More systems and equipments, so easy to cause equipment corrosion problem, how to effective convergence engineering and operation corrosion, promote anti-corrosion integration management control and to ensure equipment safety, quality and reliability, TNPJVC created a set of applicable to whole life period of anticorrosion management system. The practical results obtained good expectations.
出处
《全面腐蚀控制》
2016年第1期1-4,66,共5页
Total Corrosion Control
关键词
CEPR
防腐
一体化
管理
CEPR
anticorrosion
integration
management