新建贵广铁路1/42道岔施工方案比选及关键施工技术

Construction Scheme Selection and Key Construction Technology for 1/42 Turnout of Newly Built Guizhou-Guangdong Railway
下载PDF
导出
摘要 在行车密度大,施工场地狭窄的条件下,对新建贵广铁路老罗堡联络线1/42有砟道岔进行施工并确保安全,其难度较大。为此,在比较各种施工方案的基础上,确定了区间整体插铺、分级提速的施工方案。重点介绍了线外道岔整体预拼、轨道形位控制、轨排加固、横移及起升同步控制系列技术。工程实践表明:该方案保证了施工质量和行车安全。 Under the condition of high rate of traffic flow,narrow construction space and safety protection,the construction of 1 /42 ballast turnout in Laoluobao connecting line of newly-built Guizhou-Guangdong Railway is quite difficult. Therefore, based on various construction schemes, the construction scheme for overall pavement and classified acceleration in the space was confirmed. The overall pre-assembly out of the turnout,track shape control,track skeleton reinforcement,sidesway and lifting synchronous control series technology were mainly introduced. The engineering practice shows that the construction scheme can ensure construction quality and traffic safety.
作者 王强
出处 《路基工程》 2016年第1期163-167,共5页 Subgrade Engineering
关键词 新建铁路 1/42有砟道岔铺设 施工方案比选 整体插铺 关键技术 Newly built railway pavement of 1/42 ballast turnout construction scheme selection overall pavement key technology
  • 相关文献

参考文献5

二级参考文献20

  • 1杨宏伟,孙柏辉.客运专线高速道岔铺设技术探讨[J].铁道标准设计,2009,29(S1):16-18. 被引量:6
  • 2中华人民共和国铁道部.铁建设函[2003]205号新建铁路桥上无缝线路设计暂行规定[S].北京:中国铁道出版社,2003.
  • 3中华人民共和国铁道部.TB10621--2009,J971--2009高速铁路设计规范(试行)[D].北京:中国铁道出版社,2010.
  • 4中华人民共和国铁道部.TB10002.3-2005,J462--2005铁路桥涵钢筋混凝土和预应力混凝土结构设计规范[S].北京:中国铁道出版社,2007.
  • 5中华人民共和同铁道部.客运专线铁路无砟轨道铺设条件评估技术指南[S]北京:中国铁道出版社,2006.
  • 6中华人民共和国铁道部.铁路混凝土结构耐久性设计暂行规定[S]北京:中国铁道出版社,2005.
  • 7中华人民共和国铁道部.客运专线无砟轨道铁路工程测量技术暂行规定[S]北京:中国铁道出版社,2006.
  • 8中华人民共和国铁道部.铁路混凝土工程施工质量验收补充标准[S]北京:中国铁道出版社,2006.
  • 9中华人民共和国铁道部.TB 10424-2003 .铁路混凝土与砌体工程施工质量验收标准铁路混凝土与砌体工程施工质量验收标准[S].北京:中国铁道出版社,2003.
  • 10中华人民共和国铁道部.客运专线无砟轨道铁路工程施工质量验收暂行标准[S]北京:中国铁道出版社,2007.

共引文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部