摘要
针对高层住宅电气竖井空间较小,而在建筑电气设计中对电气竖井布置及预留预埋,乃至主体完工后的设备安装没有详细设计的问题,指出电气竖井深化设计的必要性。以某住宅项目为例,总结在主体施工前电气竖井深化设计的考虑因素和具体做法。
This article points out the necessity of a deepened design of electric shaft, and summaries the factors to consider and specific practices regarding deepening the design of electric shaft before construction of main part by taking a residential project as an example, aiming to solve the problems of small space for electric shaft in high-rise residential buildings and unavailable detailed design for the arrangement, reservation and pre-bury of electric shaft, and for equipment installation even after the completion of the main part.
出处
《建筑电气》
2016年第2期58-62,共5页
Building Electricity
关键词
高层住宅
电气竖井
电缆桥架
管线预埋
防火密封隔离
强电系统
弱电系统
火灾自动报警系统
electric shaft
cableresistant sealing andweak current system
high-rise residential building
bridge
pipeline pre-bury
fireisolating
strong current system