摘要 鉴于电气一次设备在设计、制造、安装及试验等方面的质量控制好坏直接影响着机组投产发电目标能否顺利实现,介绍了呼和浩特抽水蓄能电站电气一次设备安装项目管理过程中出现的具有代表性的问题及缺陷,对相关原因进行了分析,提出了处理措施,并针对性地进行了总结及反思,可供相关工程参考。 Quality control of the design, manufacture, installation and trial test of the primary electrical equipment in power stations will directly affect the operation of the generator units. Thus, management experience of the primary electrical equipment installation project in Hohhot Pumped Storage Power Station is summarized. Several typical issues are diseussed and corresponding treatment measures are proposed. It could be a useful reference for similar projects.
作者 许捷
出处 《水电与新能源》 2016年第2期55-57,共3页 Hydropower and New Energy
关键词 抽水蓄能电站 电气一次 安装项目管理 总结 反思 Hohhot Pumped Storage Power Station primary electrical equipment installation project management summary introspection
  • 相关文献

参考文献4

共引文献31

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部