摘要
对硐室过去支护方式及破坏机理进行综合分析,获得围岩变形破坏的机理。现采用格栅钢架配合高强度、高预紧力锚网索联合支护对变形破坏硐室进行修复,并合理设计支护参数,改进后的施工设计方案有效地控制了硐室围岩的变形破坏。
Cmprehenslvely analyzed the supporting mode and failure mechanism of chamber in the past and obtained surrounding rock deformation and failure mechanism. Now through the Use of high prestressed high strength grid steel frame and anchor net cable combined support to repair deformation and failure chamber,and the rational design of the supporting arguments,then the improved construction design scheme have effectively controlled the deformation and damage of surrounding rock.