摘要
为了快速推过大断层,在研究深井综放工作面断层产状的基础上,确定了合理过断层方案,提出了过断层新的技术理念,合理优化组织生产,保证了回采速度,减少了煤炭资源损失,有效控制了设备事故率,保证了安全生产。
To quickly pass through large fault, based on the study of fault occurrence in fully-mechanized caving working face of deep mine, Reasonable scheme of passing through large fault is determined, The new technology idea of passing through fault is put forward, Rationally optimizing the organization of production,ensure the recovery rate,reduce the loss of coal resources,effectively control the accident rate of the equipment,and ensure safe production.
出处
《山东煤炭科技》
2016年第3期61-63,共3页
Shandong Coal Science and Technology
关键词
深井
综放工作面
过大断层
passing through large fault deep mine fully-mechanized caving working face