浅谈挂篮施工0#块临时锚固和支架体系的优化 被引量:3

Elementary Discussion on Optimization of 0# Provisional Anchorage and Bracket System Constructed by Traveling Form
下载PDF
导出
摘要 以海西高速公路网东山联络线A标段的东山特大桥为背景,对东山特大桥主桥0#块现浇支架、临时锚固体系进行了方案优化及对比。优化后的方案采用简单的混凝土立柱代替传统的钢管混凝土支撑体系,提高了施工安全性加快了施工进度同时又降低了施工成本。 Taking Dongshan Bridge in Bid A of Dongshan Liaison Line in Haixi Expressway as thebackground, the article introduces the scheme optimization and comparison of the main bridge 0# cast-in-situ bracket and provisional anchorage system of Dongshan Bridge. The optimized scheme uses the simple concrete column instead of the conventional concrete filled steel tube support system, which improves the construction safety, speeds up the construction schedule and also reduces the construction cost.
作者 郭小兵
出处 《城市道桥与防洪》 2015年第12期118-119,14-15,共2页 Urban Roads Bridges & Flood Control
关键词 挂篮 悬浇 临时锚固 0#块 优化 traveling form cantilever pouring provisional anchorage 0# block optimization
  • 相关文献

参考文献3

  • 1海峡西岸经济区高速公路网东山联络线两阶段施工图设计(第三册)[z].
  • 2东山特大桥临时工程主墩临时锚固及噼块支架施工图[z].
  • 3JTG/T 50—2011,公路桥涵施工技术规范[S].

共引文献10

同被引文献19

引证文献3

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部