摘要
透水框架护岸是将透水框架铺设在岸坡坡面上,利用透水框架的减速促淤机理来防护岸坡。本试验开展了四面六边透水框架和扭双工字型透水框架铺设在岸坡坡面上的试验研究,对其护岸效果、减速促於机理进行分析,了解透水框架护岸的优缺点,分析透水框架护岸的应用部位。
To protect the slope, penetrating frames, which have the effect of deceleration and accretion promotion,are laid on the slope surface for bank protection. Carrying out the experiments of bank protection by laying tetrahedron-like penetrating frame and twist double H permeable frame on the bank slope surface,we analyze the effect of bank protection and mechanism of deceleration and accretion promotion and recognize the advantages and disadvantages and the applying position of bank protection by penetrating frames.
出处
《水运工程》
北大核心
2016年第3期112-119,共8页
Port & Waterway Engineering
关键词
四面六边透水框架
扭双工字型透水框架
护岸
防冲促淤
tetrahedron-like penetrating frame dam
twist double H permeable frame
bank protection
deceleration and accretion promotion