摘要
本文结合工程经验,首先分析了单层索网玻璃幕墙的施工流程,并从基础测量放线、后置埋件设置与钢结构安装、锚具锚固与拉索夹具安装、荷载试验、玻璃面板安装、耐候胶施注等方面进行了深入探析,尤其对预应力三级张拉结构拉索节点调整及拨接系统精确定位等关键技术进行了深刻思考,旨在为今后其他单层索网玻璃幕墙工程的施工技术应用提供经验和帮助。
Combining engineering experience, the first analysis of the monolayer cable net glass curtain wall construction process, from basic Surveying, rear buried pieces of setup and installation of steel structures, anchors and anchor cable clamp installation, load test, the glass panel installation, weathering plastic injection facilities and other aspects of depth, especially for prestressed three tensioning cable node structure adjustment and dial-up systems and other key technology for precise positioning of the deep thinking, it aims for the future other monolayer cable net glass curtain wall construction technology applications engineering experience and provide assistance.
出处
《建筑技术开发》
2016年第3期96-98,共3页
Building Technology Development
关键词
单层索网
玻璃幕墙
施工技术
monolayer cable net
glass curtain wall
construction technology