摘要
随着工作水深的不断提高,自升式平台拔桩作业显得尤为重要。在没有详细计划的情况下,拔桩作业充满挑战和危险。历史上发生的多起自升式平台拔桩事故都与拔桩阻力预测的偏差有直接关系。文中分析拔桩和冲桩的过程和原理,提出冲桩系统的优化方案和发展建议,使该系统更能有效地辅助拔桩作业。
With the working depth of the jack-up platform increasing continuously, the operation of pulling-out the pile becomes more and more important. If no detail information about the soils is known, the pile extraction will be confronted with danger and challenges. Many accidents about pile extraction have something to do with the deviation of the resistance forecast of pile. The process and principle of the pile extraction are analyzed to propose optimizing solutions and development proposals for the pile extraction and jetting operation of the jack-up unit.
出处
《船海工程》
北大核心
2015年第B11期156-158,163,共4页
Ship & Ocean Engineering
关键词
自升式平台
拔桩
冲桩
jack-up
pile extraction
jetting system