摘要 针对林南仓矿-650m水平二采区村庄下条带开采,采用FLAC^(3D)数值模拟方法进行了模拟分析设计,分析了覆岩移动和破坏过程,认为在中硬互层型的岩层结构、极不充分开采条件下,在上覆岩层中形成了稳定的拱型平衡结构,在平衡拱内岩石破坏、垮落,在平衡拱外岩层弯曲变形。依据数值模拟结果,设计了林南仓矿极不充分开采方案,对煤柱稳定性进行了分析,FLAC^(3D)计算结果表明当煤柱宽度达到70m时,可以将两个极不充分开采工作面隔离成相对独立的开采工作面,能有效地控制地表的移动和变形。 Strip mining was applied in the second mining area that under village at -650m level of Linnancang coal mine, numerical simulation analysis and design were done by numerical simulation method RFPA, overburden movement and broken process were ana-lyzed, stable arch balance structure formed in overburden under medium harden interlayer rock structure and extremely inadequate mining condition, rock broken appeared in balance arch, rock bend deformation appeared out of balance arch.Mining method of ex-tremely inadequate mining of Linnancang coal mine was put forward on the basis of numerical simulation, coal pillar stability was ana-lyzed, the results of FLAC3D simulation showed that two extremely inadequate mining working faces would be isolated to a relative inde-pendence working face, when coal pillar width was 70m, then surface movement and deformation could be controlled effectively.
出处 《煤矿开采》 北大核心 2016年第2期69-72,117,共5页 Coal Mining Technology
基金 国家自然科学基金资助项目(51404272)
关键词 极不充分开采条件 开采宽度设计 FLAC3D 数值模拟 条带开采 extremely inadequate mining mining width design FLAC3D numerical simulation strip mining
  • 相关文献

参考文献8

二级参考文献16

共引文献20

同被引文献19

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部