浅析挂篮施工法——记津保铁路120m连续梁菱形挂篮施工 被引量:1

Analysis on the Cradle Construction:Rhombic Cradle Construction of 120m Continuous Beam of Jinbao Railway
下载PDF
导出
摘要 津保铁路子牙河特大桥主桥为(76+4×120+76)m连续梁桥,本文介绍了该桥的主要结构特点,以及菱形挂篮施工法在该桥主体结构上的运用,从挂篮的结构特点以及从模板、钢筋、混凝土、预应力等施工方面介绍了其施工特点,同时也阐明了施工中的一些重难点和控制要点,为挂篮在大跨度连续梁施工方面给出点借鉴意义和参考。 The main bridge of Jinbao Railway Ziya River Bridge is(76+4×120+76)m continuous girder bridge. This paper introduces the main structure characteristics of this bridge, and the application of rhombic cradle construction in the main structure of the bridge,introduces its construction characteristics from the structure characteristics of the hanging basket, template, steel, concrete, prestressed and other construction aspects. At the same time, this paper illustrates the difficult points and key control points of the construction to provide reference for the hanging basket in the construction of large-span continuous beam.
作者 李亮
出处 《价值工程》 2016年第12期103-106,共4页 Value Engineering
关键词 挂篮 后锚 T构 模板 钢筋 混凝土 预应力 线形 合拢 hanging basket back anchor T-structure template rebar concrete prestress linear fold
  • 相关文献

参考文献7

  • 1TB10230-2002,铁路桥涵施工规范[S].中国铁道出版社.
  • 2TB10002.3-2005-铁路桥涵钢筋混凝土和预应力混凝土结构设计规范[s].2005.
  • 3范立础.桥梁工程(上册)[M].二版.北京:人民交通出版社.
  • 4赵青山.菱形挂篮的研制及应用技术[J].施工技术,1994(3):21-26.
  • 5中铁三局集团有限公司.铁建设[2010]241号高速铁路桥涵工程施工技术指南[S].
  • 6TB10752-2010高速铁路桥涵工程施工质量验收标准[S].
  • 7范立础.桥梁工程(下册)[M].二版.北京:人民交通出版社.

共引文献75

同被引文献13

引证文献1

二级引证文献15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部