FPSO单点锚系海上安装工艺方法研究

Installation Processes and Methods for FPSO Mooring Line
下载PDF
导出
摘要 根据南海某油田开发群项目单点系统海上安装实例,研究内转塔式单点锚系海上安装的工艺方法,总结海上施工经验,对实际安装工艺中存在的问题进行优化,为今后同类项目开展提供参考。 The single point mooring line is the main part of FPSO. The paper mainly researches the mooring line installation processes and methods according to the actual installation example. It is very complex and also a high risk for the installation process of internal turret mooring line. And there are many uncontrolled factors. This paper mainly summarizes the installation process, according to the actual project, at the same time gives improvements for the existing problems. It provides reference for the future similar project.
出处 《机械工程师》 2016年第4期229-232,共4页 Mechanical Engineer
关键词 锚桩 海上安装 单点锚系 配重链 钢缆 倒缆器 ROV anchor pile offshore installation single point mooring line counterweight chain steel cable spooler ROV