新庄煤矿大直径立井快速施工 被引量:1

Rapid Construction of Mine Large Diameter Shaft in Xinzhuang Mine
下载PDF
导出
摘要 甘肃新庄煤矿主立井,净直径9 m,井深790.5 m,冲积层厚30 m,冻结深度673m。井筒冻结段掘进直径最大达13.4m,每循环需出矸900m3(段高4m);井壁最厚处达2.2m,每m井壁需浇筑混凝土77.5m3。井筒冻结段掘砌施工中,采用8臂伞形钻架钻眼、甩吊桶法出矸、溜灰管下混凝土等新技术、新工艺,加快了施工速度,仅用7个月就施工到底,取得了平均月进尺超过90m、最高月进尺达110m的好成绩。 A mine main shaft of Gansu Xinzhuang Mine had a net diameter of 9 m,a shaft depth of790.5m,an alluvium thickness of 30 mand a freezing depth of 673 m.At the mine shaft freezing section,a max excavation diameter was 13.4mand each operation cycle(a section of 4 m)would have900m3 of wastes to be discharged.A max thickness of the mine shaft liner was 2.2mand each meter height of the mine shaft liner would need the casted concrete of 77.5 m^3.During the excavation and lining operation of the mine shaft freezing section,there was a 8boom umbellate drilling rig applied to the borehole drilling and a fling sinking bucket method for the waste discharging,a chute line for the concrete downward transportation and other new technology and technique applied made the construction speed fast.The mine shaft sinking construction was reached to the bottom of the mine shaft only with seven months,an average month sinking rate was over 90 mand a max month sinking rate was110 m.
出处 《建井技术》 2016年第1期5-7,共3页 Mine Construction Technology
关键词 大直径立井 快速施工 新工艺 8臂伞形钻架 mine large diameter shaft rapid construction new technology 8boom umbellate drilling rig
  • 相关文献

参考文献3

二级参考文献2

  • 1龙志阳.千米深井凿井技术现状及发展新动向[A].周兴旺主编.矿山建设工程技术新进展论文集[c].徐州:中国矿业大学出版社,2009.
  • 2龙志阳.立井井筒施工技术[M].北京:煤炭工业出版社,1999..

共引文献49

同被引文献5

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部