摘要 1000kV特高压长治站是我国首个特高压工程的起点站,连接华北与华中两大电网,特高压长治站500kV侧HGIS设备漏气较为频繁,给系统安全运行造成不小压力。主要介绍一起典型的500kV新型高压开关设备HGIS(Hybird Gas Insulated Switchgear)漏气缺陷的分析与处理,通过对漏气原因的分析,根据现场实践经验,制定了相应的预防、解决措施,具有较强的应用价值。 1000 kV UHV Changzhi substation is the initial station of the first UHV transmission project in China. The UHV transmission line links North China Power Grid and Central China Power Grid. However, gas leakage occurs frequently at 500 kV side of Changzhi substation, which poses a big threat to the safe operation of the system. This article is focused on the analysis and treatment of a typical gas leakage accident of a 500 kV HGIS. According to the analysis on the causes of leakage, corresponding measures are put forward for prevention and solution, which has great value in application.
作者 高吉 郭希昌
出处 《山西电力》 2016年第2期50-51,共2页 Shanxi Electric Power
关键词 HGIS 漏气 SF6 特高压 HGIS(Hybrid Gas Insulated Switchgear) leakage SF6 UHV
  • 相关文献

参考文献3

  • 1上海市电力公司.气体绝缘金属封闭开关设备运行及维护规程:DL/T603-2006[s].北京:中国电力出版社,2006.
  • 2国电北京电力建设研究所.电气装置安装工程电气设备交接试验标准:GB50150--1991(s].北京:中国计划出版社,2006.
  • 3曲文韬,黄锐,吕俊涛.220kV GIS设备漏气原因分析及预防措施[J].电力科学与工程,2013,29(8):21-26. 被引量:30