以方家山核电站M310核电机组主管道安装为例,介绍了主管道焊接安装的方案,对主管道焊接工期进行了评估,分析了影响主管道焊接作业的主要因素,提出了焊接施工的注意事项以及工期优化措施。
Taking major pipeline installation of Fangjiashan nuclear power station M310 nuclear power unit as an example,the paper introduces the major pipeline welding installation scheme,evaluates the major pipeline welding duration,analyzes major factors influencing major pipeline welding,and finally puts forward welding matters and construction duration optimizing measures.
出处
《山西建筑》
2016年第11期111-112,共2页
Shanxi Architecture
关键词
核电站
主管道
焊接
工期
nuclear power station
major pipeline
welding
construction duration