摘要
介绍了2013清单中合同价款的约定内容,分析了引起合同价款调整的因素,从工程变更、工程量偏差、物价变化等方面,阐述了容易产生争议的因素及调整原则,为清单价款调整问题提供了解决方法。
This paper introduced the agreement contents of 2013 listing contract price,analyzed the factors caused contract price adjustment,from the engineering change,quantities deviation,prices change and other aspects,elaborated the factors and adjustment principle easy to cause generate controversy,provided solution to listing price adjustment problems.
出处
《山西建筑》
2016年第11期242-243,共2页
Shanxi Architecture