巴西巴拉那瓜工程是一项极具代表性的维护工程项目。之前中港疏浚有限公司在巴拉那瓜施工多年,期间遇到各种问题,也采取了很多方法,但效果不佳。本文通过2013年11月至2014年11月新海牛轮在巴西巴拉那瓜工程各区段的施工情况,分析了每段的施工方法、施工重、难点等,确定出针对不同的施工工况采取不同的措施。
Abstract: Paranagua engineering in Brazil is a very representative maintenance project. Before that, CHEC Dredging Co.,Ltd. had carried on construction for many years at Paranagu6, encountered various problems, and also taken a lot of methods, but the results were bad. Through the every segment construction situation of Brazil Paranagua engineering in the charge of Xinhai Cattle Ship Company from November 2013 to November 2014, this paper analyzes the every segment construction methods, emphasis and difficulty etc., and determines different measures for different construction conditions.