摘要
介绍了遇水沟和电缆沟时接触网基础的各种处理方式,其中倒L形偏心基础既能避免水沟和电缆沟的影响,又能保证支柱的侧面限界,为接触网工程中首次采用,可在相关工程中推广。
The paper introduces various treating measures when OCS foundations are encountered with the water ditches and cable trenches, among which, the inverted L eccentric foundations are able to not only avoid the water ditches and cable trenches related influences, but also guarantee the side gauge of the mast, they have been adopted for the OCS engineering for the first time and may be applied in the similar projects.
出处
《电气化铁道》
2016年第2期26-27,32,共3页
Electric Railway
关键词
接触网
基础施工
基础倾覆稳定
倒L形基础
穿水沟基础
OCS
foundation construction
foundation overturning stability
inverted L foundation
trench-through foundation