摘要
为了提高变电站的施工管理水平,引入建筑信息化模型(BIM)技术,以某典型的220 kV变电站施工为实例,运用Revit软件建立变电站的三维可视化模型,并对其施工过程进行4D仿真模拟.根据模拟结果,提出了BIM技术在变电站施工中的实施路径和框架.考虑到变电站主要设备噪声对周边环境的影响,分析了所建立的BIM变电站模型对变电站噪声的影响,并对变电站的规划设计进行了优化控制,取得了较好的效果.
In order to improve construction management of 220 kV substation construction project,the BIMtechnology is introduced and visualizing model of the 220 kV substation is built to make 4D simulations of the project.According to the simulation results,the authors propose the BIMframework and path of the implementation of the project management.Considering the effect of the main substation equipment noise on the surrounding environment,the authors analyze the impact of the substation noise by using BIMand achieve good results through the application of layout optimization control of substation noise at the planning stage.
出处
《上海电力学院学报》
CAS
2016年第2期193-198,共6页
Journal of Shanghai University of Electric Power
关键词
BIM技术
变电站工程
4D施工仿真
噪声控制
BIM technology
substation construction
4D construction simulation
noise control