铁路专用线接轨一般选择在相邻铁路线上已开通货运、具备接轨技术条件的国铁车站,在编组站接轨往往因为受限较多而无法实施。以新建合肥热电集团铁路专用线为项目依托,分析影响新建铁路接轨方案的主要因素,阐述合肥东编组站和东方热电厂的主要概况,从技术因素、经济因素、环境因素及社会因素4个方面对东方热电厂铁路专用线在合肥东编组站接轨的可行性进行研究探讨。
Junction of railway industrial siding is generally selected on national railway station of adjacent railway line, which has opened freight transportation and was provided with technical conditions of junction, and the junction selected on marshalling station often cannot be implemented because of much restriction. Relying on the project reference of new constructed railway industrial siding in Hefei Thermal Power group,,the paper analyzes main factors influencing the junction program of new constructed railway, and expounds main profile of Hefei East Marshalling Station and Oriental Thermal Power Plants, and studies the feasibility of making junction of railway industrial siding of Oriental Thermal Power Plants in Hefei East Marshalling Station from 4 aspects, including technical factors, economic factors, environment factors and social factors.
出处
《铁道货运》
2016年第4期43-46,56,共5页
Railway Freight Transport
关键词
编组站
接轨可行性
影响因素
货运服务
Marshalling Station
Feasibility of Junction
Influence Factor
Freight Transport Service