摘要
论述了高路堤的设计和施工技术,包括路堤横断面设计、路堤填料选取、压实标准、压实机具的选择、冲击碾压部位及要求等,并辅以工程实例进行了说明,旨在为高路堤设计与施工参考。
The design and construction technology of high fill subgrade are discussed, including cross section design of subgrade, subgrade impact rolling part and design and construction filler selection, compaction standard, selection of compaction machines and tools, requirement and so on, and the project case is illustrated, thus providing reference for of high fill subgrade.
出处
《北方交通》
2016年第4期129-131,135,共4页
Northern Communications
关键词
高填方
路堤
压实度
High fill
Subrade
Degree of compaction